The following CPM network has estimates of the normal time
The following CPM network has estimates of the normal time
The following CPM network has estimates of the normal time in weeks listed for the activities:
a Identify the critical path.
b What is the length of time to complete the project?
c Which activities have slack and how much?
d. Here is a table of nominal and crash times and costs. Which activities would you shorten to cut two weeks from the schedule in a rational fashion? What would be the incremental cost? Is the critical path changed?