The following activities are part of a project to be

The following activities are part of a project to be

The following activities are part of a project to be scheduledusing CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 4C A 8 D C 5 E BPicture D 3 F D 6 G EPicture F 3 b. What is thecritical path? A-B-E-G A-B-D-F-G A-C-D-E-G A-C-D-F-G c. How manyweeks will it take to complete the project? Number of weeks d. Howmuch slack does activity B have? Slack of activity B week(s) Attached