Task time estimates for the modification of an assembly line at Jim GoodaleAc€?cs Carbondale, Illinois, factory are as follows
Activity Time
(In hours) Immediate
Predecessot(s)
A
6.0
–
B
7.5
–
C
6.0
A
D
5.0
B,C
E
4.5
B,C
F
6.5
D
G
4.0
E,F
This exercise contains only part d,b,and c
d) Using the line drawing tool five times draw a Gantt chart for activities C through G of the ptoject based on early times
Carefully follow the instructions above and only draw the required objects