Cost Benefit Calculation_Agile Project Management
Cost Benefit Calculation_Agile Project Management
Using the table of costs and benefits below, answer the questions that follow.
Year
Costs
Benefits
Year 0
1,000,000
20,000
Year 1
125,000
50,000
Year 2
25,000
100,000
Year 3
25,000
120,000
Year 4
25,000
140,000
Year 5
25,000
160,000
Year 6
25,000
180,000
Year 7
25,000
200,000
Year 8
25,000
220,000
Year 9
25,000
240,000
Year 10
25,000
260,000
Year 11
25,000
280,000
Year 12
25,000
300,000
Year 13
25,000
320,000
Year 14
25,000
340,000
Year 15
25,000
360,000
Year 16
25,000
380,000
Year 17
25,000
400,000
Year 18
25,000
420,000
Year 19
25,000
440,000
Year 20
25,000
460,000
Year 21
25,000
480,000
Year 22
25,000
500,000
Year 23
25,000
520,000
Year 24
25,000
540,000
Year 25
25,000
560,000
1. What is the NPV(Net Present Value) of the project? Assume a 15% discount rate and round your answer to the nearest whole dollar (e.g. $125,321).
2. What is the IRR(Internal Rate of Return) of the project? Round your answer to two decimal places (e.g. 15.80%).
3. What is the Simple ROI(Return on Investment) of the project?
4. Based on your calculations, should the project move forward? Why or why not?
Please submit a single Excel file with your answers. Please answer the questions directly in the Excel file.
Like this:Like Loading…
"You need a similar assignment done from scratch? Our qualified writers will help you with a guaranteed AI-free & plagiarism-free A+ quality paper, Confidentiality, Timely delivery & Livechat/phone Support.
Discount Code: CIPD30
Click ORDER NOW..