1. The difference between the upper specification and the lower specification for a process is 0.6″. The standard deviation is 0.1″. What is the process capability ratio, Cp? Interpret this number.
2. Meena Chavan Corp.’s computer chip production process yields DRAM chips with an average life of 1,800 hours and s = 100 hours. The tolerance upper and lower specification limits are 2,400 hours and 1,600 hours, respectively. Is this process capable of producing DRAM chips to specification?
 